Experimental power transmission to the national grid has begun for a second time from the under-construction Rooppur Nuclear Power Plant in Ishwardi, Pabna.
Power transmission from the plant’s first unit began at 10:20 a.m. on Monday (23 November).
Rooppur Nuclear Power Plant Construction Project Director Dr Md Kabir Hossain said approximately 300 to 350 megawatts of electricity would be supplied to the national grid on an experimental basis for 10 to 24 hours during the second phase. During this period, various technical tests will be conducted on the power plant’s generation system and its integrated operation with the national grid.
Earlier on 17 November, experimental power supply to the national grid began from the Rooppur Nuclear Power Plant for the first time. In the first phase, a maximum of 375 megawatts was generated from the first unit and supplied to the national grid for about eight and a half hours. The estimated market value of that electricity was around Tk 2 crore. The grid connection was later disconnected at 11:50 p.m.
Nuclear Power Plant Company Bangladesh Limited (NPCBL) Managing Director Dr Md Zahedul Hasan said the efficiency and stability of the turbine, generator, and integrated operation with the national grid were closely monitored during the initial grid synchronization. As test results were satisfactory, the grid connection was restored for the second phase following a necessary interval.
He said, “In the second phase as well, the grid connection will be disconnected taking overall conditions into account after several hours of monitoring. Electricity generation will be scaled up or down according to need in subsequent tests. The unit may also need to be shut down temporarily for certain tests. Power Grid Bangladesh PLC (PGB) will take necessary measures to maintain grid balance amid generation fluctuations.”
Praising the dedication of NPCBL engineers, scientists, officers, and staff, the managing director further noted that all-out efforts are underway to supply electricity to the national grid at full capacity from the first unit ahead of next summer, between February and March 2027. He expressed hope that around 1,150 megawatts of electricity would be supplied at that stage, anticipating that it would significantly alleviate the country’s power shortage next summer.
Project officials said grid connection is a critical technical milestone in synchronizing the power plant’s generation system with the national transmission network. However, initiating experimental power transmission does not signify that the plant has entered full commercial operation.
Power generation capacity will be increased in phases following International Atomic Energy Agency (IAEA) guidelines and global safety benchmarks. After completing essential testing, licensing, and regulatory approvals, authorities aim to gradually scale the first unit’s generation capacity to 100 percent.
Two units with a capacity of 1,200 megawatts each are being constructed at the Rooppur Nuclear Power Plant in Bangladesh. Once both units are operational, the facility’s total generation capacity will reach 2,400 megawatts. Stakeholders view the commencement of the second round of experimental power supply as another significant step forward in the country’s nuclear power generation journey.