About 120 meters of a newly repaired embankment in the Tetulbaria-Nalbania area of Barguna is collapsing into the Payra River because of underwater erosion and strong currents, officials said.
Large cracks have also appeared along about 120 meters of the flood-control embankment. Residents fear high tides could breach it and flood homes and farmland unless urgent work is undertaken. They called for a permanent embankment.
The Water Development Board repaired 590 meters of embankment and placed geobags in five packages. The work, completed on September 21, had a contract value of Tk 1 crore 47 lakh 74 thousand.
Popular Construction completed two packages in fiscal 2025-26. RS Construction, Sohel Enterprise and Moni Traders worked on three packages in fiscal 2026-27. Two current-year packages were damaged and another developed cracks, according to the account.
A site inspection found recently placed geobags and piled embankment sections sliding into the river. Cracks extended for about 200 meters in places, with soil washed away and inner sections exposed.
Water Development Board Executive Engineer Hannan Pradhan said the river had been farther from the embankment during construction. Geobags were placed on the slope to protect it from rough waves during a maritime depression.
Underwater erosion had since begun at the site, he said. More geobags and blocks were needed in the river, but no immediate budget was available. A proposal had been submitted for a durable embankment using concrete blocks and geobags.