COX'S BAZAR, Nov. 27 — Bangladesh Petroleum Exploration and Production Company (Bapex) has brought under control a natural gas fire that burned for 31 days straight at Inani in Ukhiya, Cox's Bazar.
The fire was brought under control at around 9 a.m. on Friday (Nov. 27) in a final operation by a team of specialists. They succeeded by installing a 30-inch casing pipe and diverting the flow of gas.
The success has brought relief to local residents after a month of fear. Although the fire is under control, work to control the gas pressure inside the well and seal it permanently still remains.
A 55-member Bapex team of specialists ran the operation for about 14 days. Working long hours each day, they brought the gas flow under control with local technology and their own staff.
On Oct. 27, water and then gas began to come out of the ground while a deep tube well was being installed in the Chhotokhal area of Jaliapalong union in Ukhiya. At one point the gas caught fire, and it had burned continuously since then.
It was first thought to be a limited pocket of gas, but as the flow continued for a long time, discussion began on the possibility of a large gas reserve underground. No final announcement of a commercial gas field discovery has been made yet.
Alongside bringing the fire under control, Bapex has begun an initiative to explore for gas at Inani and nearby areas. A geological survey is planned initially across an area of two to three kilometers, and preparations are reported to be under way to start the survey in December.
Geological and seismic surveys will assess the location, extent and size of the gas underground and the feasibility of commercial extraction. If the results are positive, a decision to drill an exploration well could follow.
The use of Bapex's own technology and staff to control the Inani fire is drawing particular attention. By the estimates of those involved, the domestically managed operation may cost about Tk 1 crore to 2 crore. Help from a foreign company could instead have cost about Tk 100 crore to 150 crore.
The Inani incident is no longer only about controlling a fire; it has raised questions about a new possibility for the country's energy security. If there is gas underground, how far it extends, how much is recoverable and whether extracting it would be commercially viable can only be answered through exploration and scientific testing.
Experts say an area cannot be called a gas field just because gas is seen escaping at first. That requires geological analysis, seismic surveys, drilling an exploration well and measuring the gas reserve and pressure.
While Bapex's success in controlling the fire is welcome news, Inani's real importance depends on proving the size and commercial viability of the gas underground.